Sliding tariffs mean more power, but is the trend sustainable?
A number of strong factors are boosting the growth of solar and wind power in India, but doubts persist over viability

“This is the kind of paradigm shift that has taken place in India’s energy sector,” says Munjal. “Renewables are now the preferred source of power in India, not just due to issues of morality and ethics, but because it is economically viable.” FY2016-17 has seen the addition of a record amount—more than 11 GW (1 GW equals 1,000 MW)—of RE capacity, mostly in the solar (5,526 MW) and wind power (5,400 MW) sectors it has, for the first time, caught up with thermal power capacity added during the same period.
This is a long way from a decade ago when RE technology was expensive and tariffs high—Rs17 per kWh (kilowatt hour), compared to Rs3-4 for thermal power. “There was criticism that RE wasn’t a business to be done and there was doubt about whether India will even reach the earlier RE target of 20 GW that it had set for itself,” says Inderpreet Wadhwa, CEO of Azure Power, an India-focussed clean energy firm.
But, over the last few years, a concerted governmental push to promote clean energy, access to advanced and cheap technology (such as solar photovoltaic cells from China), and the availability of global equity funding have made RE a sunrise sector. In 2009-10, the government’s target of installing 20 GW by 2022 had appeared impossible. Compared to that, the present government, in 2015, revised the target to 175 GW by 2022. Consequently, the sector has received investments of $14 billion (debt and equity) in 2016-17, double of what it had received in the previous fiscal.
Since 2010, solar power tariffs have fallen by more than 75 percent. In 2017, tariffs for projects awarded through a reverse bidding process by state and central governments have touched a new low twice: In February, the tariff for a 750 MW project in Rewa, Madhya Pradesh, fell to Rs3.30 per kWh (levelised for 25 years) in April, a 250 MW project in Kadapa, Andhra Pradesh, saw tariff fall to Rs3.15 per unit in May, the lowest bid at an auction to develop 250 MW at the Adani Renewable Energy Park in Bhadla, Rajasthan, was of Rs2.71. These prices have given solar power grid-parity with thermal, making it attractive for state electricity distribution companies (discoms).
It isn’t only global investors who are eyeing India’s clean energy sector domestic companies are also taking note. Highlighting this is Tata Power’s acquisition of Welspun Energy’s clean energy capacity of 1,140 MW, last June, for Rs10,000 crore. Sardana says Tata Power’s portfolio of solar assets was “insignificant” and it would take long years for it to reach the acquired numbers organically. “The role of thermal power is to meet base-load requirements, whereas RE meets the variability above base load,” he says. “Considering that demand increase has been subdued compared to supply-side growth, thermal capacity utilisation has been adversely impacted. It is unlikely that any new thermal capacity would be added in the next few years beyond what’s in the making already.”
Flip SideBut the question is: While declining tariffs are good, at what point do they become unviable? “We aren’t confident that the current low levels [of tariff] are sustainable, given the cost of debt, even though such cost has come down in recent times,” says Ankur Ambika Sahu, co-head of Goldman Sachs’ merchant banking division in Asia Pacific. Goldman Sachs is a majority stakeholder in ReNew, and Sahu its nominee director on ReNew’s board. Such low tariffs may not continue to attract capital either. “There is bound to be a process of rationalisation when bids don’t see new capital coming in,” he adds.
Tulsi Tanti, chairman and managing director of Suzlon Energy, makers of wind turbines and a wind energy turnkey company, says that while costs and tariffs have fallen, so have margins. Earlier, expectations of internal rate of return (IRR) was high due to higher risk developers would chase an IRR of 16 to 18 percent. But now, with lower risks, developers are content with 14 to 15 percent, even 13 percent. “This is the minimum level that has to be maintained, otherwise the volume of investments will be impacted,” he says.
One of the reasons for falling tariffs is the lack of adequate projects coming up for bidding, due to a subdued demand for RE power and an abundance of coal. State discoms are also waiting for RE tariffs to stabilise, since no one wants to overpay. Discoms are also not penalised for not meeting their renewable purchase obligations. (States and union territories, collectively, fall short of their cumulative 2016-17 target by 39 percent, or close to 6,900 MW.)
Discoms also do not pay producers on time. A report by Mercom Capital Group, a clean energy market intelligence firm, estimates that discoms in Tamil Nadu, Andhra Pradesh, Rajasthan, Madhya Pradesh and Telangana have delayed payments by three to four months.
“There are a lot of underlying issues that the government needs to address, like discom financials, transmission and evacuation issues, on-time payments and payment guarantees,” says Raj Prabhu, CEO of Mercom Capital.
“Limited capacity drives fierce competition, and India is one of the best RE markets that global capital is chasing,” says Wadhwa. “So, there is some irrational exuberance.”
As on March 31, the installed capacity for solar and wind energy is close to 60 GW this means another 100 GW needs to be added over the next six years, at an average of 17 GW a year. ICRA estimates solar energy addition to increase to around 7.5 GW in FY2018, sustained by the momentum of projects already in the pipeline 40 percent of the 100 GW-target is expected to be met by rooftop solar projects. According to a report by Bridge to India, an RE consulting firm, the cumulative installation of rooftop solar in India is about 1,247 MW, as on December 31, 2016. The report estimates that 11.9 GW of rooftop capacity will be added by 2021.
The industry expects FY18 to be a lull year for wind power, with growth picking up in 2018-19. The uncertainty caused by the shift from feed-in tariffs to reverse auctions has delayed projects being tendered. Tanti, however, believes that 5 GW can be added this fiscal if more projects are announced and awarded soon.
The current pace of capacity addition will be insufficient to meet the 2022 target. At the moment, the industry is expecting the government to make a dash closer to the finishing line, and is pinning its hopes on a proactive power minister, Piyush Goyal, to channelise the tailwinds.